Front Page » July 29, 2003 » Local News » Castle Valley Special Service District
Published 3,921 days ago

Castle Valley Special Service District


Print PageEmail PageShareGet Reprints

By COREY BLUEMEL
Staff Writer

On July 17, the Castle Valley Special Service District held a meeting to update the board on its ongoing projects. The first project discussed was the chip and seal project on the Orangeville city roads. Main Street is quite rough but expected to get better when the contractor sweeps the excess gravel. The roads will then be sealed and restriped.

This project was several weeks late starting due to waiting for the curb and gutter crews to finish with their project. Darrel Leamaster pointed out that the weather is perfect for a chip/seal project as the temperature on the road surface was 136 degrees. The roads in Orangeville are expected to be completed during the week of July 21.

Concerning the SR-10 water relocation project, Terry Brotherson is the contractor and the water lines are expected to be relocated sometime during the middle of August.

The Ferron sewer lagoon relocation is waiting on the power company who are waiting on an appraisal.

The curb and gutter projects for 2003 are ahead of schedule. They are finished in Emery and Ferron, and there is a little clean up work to be completed in Orangeville. The crews will be moving into Cleveland next and then on to Elmo. At present, there are two waterways left to complete in Ferron.

Terry Brotherson is also the contractor on the drainage projects. Castle Dale is nearly completed and the projects in Orangeville are finished. The work that needs to be finished in Castle Dale are two small items that were added to the contract. These include the addition of a 15 inch drainage line on 200 North and a catch basin at 200 North and Center Street.

Nielson Construction is the contractor for the 2003 streets projects. The project is currently 33 percent complete. Emery is nearly finished and crews are working in Huntington at present. Work will continue in Huntington as soon as the utility poles have been relocated.

The applications for the 2004 CIB projects are due by Aug. 1. Leamaster and Craig Johansen will concentrate on finishing these applications to be ready on time. They have received the appropriate documents from the cities in the county. Interviews concerning the applications will take place in September with the awards to be made in December. All of the intergovernmental agreements with the individual towns have been signed and received.


Print PageEmail PageShareGet Reprints


Top of Page


 
Web Poll  
December 7, 2010
Approximately how many Emery County Progress articles per day do you view or read online?
More than 10
About 5-10
About 2-5
One
None

View Results

Provide us with feedback by visiting our community forums, by email, or by calling us at 435-381-2431.

Local News  
July 29, 2003
Recent Local News
Quick Links
Subscribe via RSS
Related Articles  
Related Stories



Best viewed with Firefox
Get Firefox

© Emery County Progress, 2000-2008. All rights reserved. All material found on this website, unless otherwise specified, is copyright and may not be reproduced without the explicit written permission from the publisher of the Emery County Progress.
Legal Notices & Terms of Use    Privacy Policy    Advertising Info    FAQ    Contact Us
  RSS Feeds    News on Your Site    Staff Information    Submitting Content    About Us
z